NA117 “Required interface documentation and staff qualifications for the installation of electrical systems“ has been revised

NAMUR Publications

Abstract to NA117 “Required interface documentation and staff qualifications for the installation of electrical systems“ (Edition: 2026-04-27)

The need for shorter lead times and closer international cooperation are ever-more important factors driving the planning and installation of new process plant equipment in order to maintain a competitive edge in the chemical and pharmaceutical industries.
Accordingly, the procurement of external installation services is also becoming increasingly important. Depending on the type of contract (fixed price or measurement and payment) and the project phase (request for quotation or ordering of installation services), different documents with different levels of detail may be required, which, as a rule, are contractually relevant. Ensuring that the customer and supplier share the same understanding based on standardised documentation is therefore crucial.
The aim of this NAMUR Worksheet is to define the interfaces between planning, installation and commissioning by specifying the minimum required documentation. This paper describes which documents are required for the tendering process, for awarding the service contract and performing the installation, for functional testing and commissioning, and defines their respective contents. The form of these documents is at the user's discretion, as this usually depends on what CAE tools are used. This way, it will be possible to commission and carry out installation services, functional testing and commissioning for PCT systems on the basis of standardised, pre-defined documents in future to ensure and document the quality of service.
This NAMUR Worksheet provides guidance for requesting a quote for and commissioning of PCT installation and functional testing services from external contractors (not for in-house handling), also in international business transactions. The underlying assumption is that the contractor is a company specialising in PCT installations.
This NAMUR worksheet does not cover the areas of energy supply and distribution or building automation.
This NAMUR Worksheet is restricted to installation-related documents; legal provisions, directives and regulations are not taken into account. This Worksheet also does not consider any other project-specific arrangements or conditions that may be stipulated in a contract for such services.